Q & A of the Day - How to carry out final connection to this congested earth bar?

Published: 11 May 2011 Category: Q&A

Our Voltimum Experts answer your questions on a daily basis in our Technical Expertise area. This Question of the Day, concerning a protective multiple earth (PME) installation with no room for the earth cable on the busbar, is answered by the ECA:

Q & A of the Day - How to carry out final connection to this congested earth bar?
Question: I'm after some practical advice here. A customer is having a protective multiple earth (PME) installed and wants me to carry out the final connection to the fuse box.

The problem is that a 16mm earth cable will not fit in the (already full) earth busbar, and he doesn't want to replace the fuse box. Do you have any ideas?

Answer: You will need to get an additional earth terminal connected to the existing earth bus bar to take the 16mm earth cable.