This Question of the Day, concerning Building Control notification of a house re-wire, is asked by Dennis Bunn and is answered by the ECA. Read on (theme - Regulations & Legislation):
This Question of the Day is on of thousands answered by our Voltimum Experts on a daily basis in the Technical Expertise area.
Question: Do I need to notify Building Control before I re-wire a domestic dwelling? Or should I notify Building Control afterwards with documentation - or both?I am not Part P registered, but I do have experience, and am trained in the 17th Edition and BS 2391.
Answer: Building Control need to be notified in advance of the work being carried out so that they may inspect it during construction.
Building Control will also want a copy of the installation certificate on completion.
To see many more Q & A in Voltimum UK's Experts Area, please click on the link:
www.voltimum.co.uk/consult.php?universe=consult.index.questions