Multi-part question: Regarding the requirements within BS7671:2001 Amm2:2004 require Main Equipotential Bonding from the Origin MET to Extraneous Conductive Parts:

1. Where a multi-occupied multi-storey office has each tenancy supplied from the landlords distribution switchboard in the basement (which already has it's own MEB applied to primary services) serving a tenant's MCB board (and where the disconnection times are the same for either 0.4s or 5s), is each of the tenant's electrical installations to be regarded as a separate electrical installation? (ie: with the 'source of supply' being at the termination each of the landlord's sub-mains and, therefore, requiring it's own MEB from the tenant's distribution board MET to services - common and/or dedicated tenants - entering the tenant's area as extraneous conductive parts. Examples in Guidance Note 8, Fig 5.17 only indicate a distributors' distributed sub-mains/service to office spaces).

2. 413-02-02 requires extraneous conductive parts to be MEB and lists service pipes etc... Is it that the parts listed must satisfy the definition of an extraneous conductive part, in that it must be liable to introduce a potential, before it is considered to require MEB? Alternatively, is it that, regardless of the definition, these parts must be bonded, (as the only real instance of central heating and air conditioning systems liable to introduce earth potentials are those that form part of a type of district heating/air conditioning system or pass between equipotential zones)?

Answer: I would suggest that each tenant's distribution board and associated installation should be regarded as a separate installation. MEB should be provided to the district heating pipework and AC ductwork at the entry position within each tenant's area.

To see many more Q & A in Voltimum UK's Experts Area, please click on the link:

http://www.voltimum.co.uk/consult.php?universe=consult.index.questions

If you like this article and want to share it with friends, please use the social links below:

 Back

 Related contacts
ECA
ECA Head Office, ESCA House,
34 Palace Court, London W2 4HY
Tel: 020 7313 4800
Fax: 020 7221 7344
Email: electricalcontractors@eca.co.uk
Web: www.eca.co.uk
blue arrow pointing right   ECA

 For latest electrical industry news, register for Voltimum's free newsletter.
Enter your email address here:
OK

Source: ECA & James Hunt

Related information

Related contacts

More News...

Fit & Run - The Lost Opportunity
Q & A of the Day - Must I segregate a fire alarm system LV supply?
Q & A of the Day – What type of conduit to use with loft wiring?
Q & A of the Day – How can discrimination be achieved with outbuildings?
Q & A of the Day - Do I need to be Part P registered?
Q & A of the Day - who is electrically competent?
Q & A of the Day - Installing a generator
Q & A of the Day - RCD neutral-phase orientation