Every day on www.voltimum.co.uk, you can find information on 20 projects planned or underway in the UK. This Project Leads service is provided by EMAP Glenigan - UK leader in the field of construction industry intelligence. It enables you to find out about projects planned or in progress in your area. You will get all the essential facts including dates and timings, locations, value and type of project and, most importantly, names and contact details of decision makers. We have selected the following project from today's 20 ....
NEWS STORY EDF Energy has appointed Carillion Plc to carry out the £5 million site establishment contract at West Burton Power Station in Retford. Work is due to commence late January 2008 for five months and involves site clearance and the construction of development platforms prior to the construction of the new West Burton Power Station. Work will also involve the provision of roads, lighting and temporary accommodation over a three year period.
PROJECT REPORT Site Establishment Works Start Date: 28th Jan 2008 Contract Period: 5 Months Project Value (Estimated)£5,000,000
LATEST INFORMATION The contract for West Burton Power Station can be viewed on project id: 06042999. CLIENT EDF Energy West Burton Power Station , Retford, Nottinghamshire, DN22 9BL Tel: 01427 882100 Fax: 01427 882200 email: info@edfenergy.com Contact: Mr Andy Lowe , FGD Section Head
CIVIL ENGG EDF Energy West Burton Power Station , Retford, Nottinghamshire, DN22 9BL Tel: 01427 882100 Fax: 01427 882200 email: info@edfenergy.com Contact: Mr Andy Lowe , FGD Section Head
CIVIL CONTRACTOR Carillion Regional Civil Engineering Fairway Court 171 Elland Road, Leeds, West Yorkshire, LS11 8BU Tel: 0113 283 0700 Fax: 0113 283 0701 email: press.office@mowlem.com Contact: Mr Dominic Cummings , Quantity Surveyor
|