Ductwork sector must tackle contractual abuse

25.10.2007
ZZ No Partner
 

Ductwork firms must take the opportunity over the next three years to tackle once and for all the contractual abuses that do great damage to their sector, according to a national M&E contractor.



This was the key message delivered by Allan McDougall, managing director of Shepherd Engineering Services, to a conference entitled Ductwork Contracting in the 21st Century and organised jointly by the Ductwork Group of the HVCA and the Association of Ductwork Contractors and Allied Services (ADCAS).

Mr McDougall added that ductwork companies often complained about their poor relationship with m&e contractors.

“Yet, I cannot remember the last time we had a dispute over a technical issue,” he added.  “More than 90% of the gripes are commercial – and now is the time to sort these out.”

Mr McDougall, who is a past president of the HVCA, added that the industry was guaranteed healthy workloads over the next three years, thanks to major government investment in schools and hospitals, plus the 2012 London Olympics programme.

And he urged all sub-contractors to ensure that their first tender price was their best price, so they could be included earlier in the design process.

HVCA Ductwork Group chairman Barry Pollard pointed out that that the ductwork sector was working on margins of between 0% and 3%, and was thereby subsidising profits further up the supply chain.

“Most industries have substantially increased their prices, but there is pressure on us to reduce ours still further because the construction industry is selling buildings at less than realistic rates,” Mr Pollard insisted.

“This financial squeeze from the top is the root cause of most of the aggravation we experience every day of our working lives.”

On a happier note, both associations acknowledged the event as a significant step forward for the sector.

“Even a year ago, such an open discussion of mutual problems could probably not have taken place,” commented ADCAS president Paul Roxburgh.

“Yet our HVCA colleagues suffer from many of the same problems that are facing us.”

The programme also featured a contribution from HVCA head of technical and safety Bob Towse on Part L of the Building Regulations, and from Professor Rudi Klein, chief executive of the Specialist Engineering Contractors’ Group, on contractual and payment issues.

The event concluded with a panel discussion chaired by HVCA chief executive Robert Higgs.


If you like this article and want to share it with friends, please use the social links below:

 Back

 Related links
blue arrow pointing right  HVCA Website

 Related contacts
Esca House
34 Palace Court
London, W2 4JG
Tel: 020 7313 4900
Fax: 020 7727 9268
blue arrow pointing right   HVCA Enquiry Email

 For latest electrical industry news, register for Voltimum's free newsletter.
Enter your email address here:
OK

Source: HVCA Website - 25/10/07

Related information

Related links
Related contacts

More News...

Davey: Next steps on collective purchasing for a better energy deal
UN Environment Chief praises London 2012's sustainability measures
HRH Prince Charles, Duke of Rothesay, opens SSE’s Barkip AD Plant
Construction Market Activity: May 2012
Balfour Beatty launches first Groupwide Sustainability Month
Inviron in the news
Add value with adult trainees
Chelsea bid for Battersea Power Station
Beatrice offshore wind farm application submitted