Q & A of the Day - Can the client insist on a TNS or TNCS supply?

BookmarkThis 17.03.2011
NICEIC
 

Our Voltimum Experts answer your questions on a daily basis in our Technical Expertise area. This Question of the Day, concerning a multi-tenancy retail unit with TNCS supply and problems of intermittent tripping, is answered by the NICEIC:

Can the client insist on a TNS or TNCS supply?
Can the client insist on a TNS or TNCS supply?
pixel
Question: In a multi-tenancy retail unit under the same metal roof, we have been supplied with a TT supply by the electricity utility company. These units are 15,000 square feet each in area and although the electricity supplier has a TN-C-S supply into the first unit, it will not give a earth connection to subsequent retail units that are looped from the first unit.

The supplier has insisted that we supply our own earth via rods, for which we have a Ze of 20 ohms on the rods only. When connected up to steel etc, we are getting a reading of 0.06 ohms. Because we have a TT system, we have installed RCD of 300mA time-delayed on the mains as per client design. However, we are getting problems of intermittent tripping, which could be caused by heating or refrigeration, or simply by the lighting control gear.

The question is, can the client insist on a TNS or TN-C-S supply, or is the client stuck with what supplier has given them?

If so, we can only remove the RCD from the mains, covering individual circuits or groups of circuits with RCDs - plus all the associated expense.

Answer: Is the structural steel in your unit bonded to your new TT earthing system? Also, is it the same structural steel frame as the TN-C-S supply to the first unit? It should be.

The 300mA RCD should not be tripping with healthy circuits and loads connected, unless there is some problem with the supply authority's neutral supply to the building, which could lead to normal load currents for the whole building returning to the transformer through the structural steel of the building creating a potential difference between your supply neutral and earth.

You cannot insist on a TN-S or TN-C-S supply, and you cannot simply remove the 300ma RCD, because you are not being provided with a sufficiently low Ze by the supplier.

I suggest that you speak to the supplier again, inform the people there that you are duty bound to connect your structural steel to your TT earthing terminal and are, therefore, connecting to their neutral earth in unit one anyway.

If they provide a TN-C-S connection within your unit, the supply neutral and earth will be connected at your origin and should prevent a potential difference occurring. Or you could try a 500mA time-delayed RCD, but that may not resolve the tripping problem.

To see many more Q & A in Voltimum UK's Experts Area, please click on the link:

www.voltimum.co.uk/consult.php?universe=consult.index.questions

 Back

 Related contacts
NICEIC Group Ltd.,
Warwick House, Houghton Hall Park,
Houghton Regis, Dunstable LU5 5ZX
Tel: +44 (0)1582 531 000
Fax: +44 (0)1582 531 010
Email: enquiries@niceic.com
Web: www.niceic.com
blue arrow pointing right   NICEIC

 For latest electrical industry news, register for Voltimum's free newsletter.
Enter your email address here:
OK

Source: NICEIC & James Hunt

Related information

Related contacts

More News...

Q & A of the Day – What are requirements for stationary equipment periodic inspection?
Q & A of the Day – Why bond to a plastic gas pipe?
Q & A of the Day – Must I install one double-pole isolator for two consumer units?
Q & A of the Day – What should be the extent of electrical testing in a wooden chalet?
Q & A of the Day – Which code for a batten holder found in a domestic bathroom zone?
Q & A of the Day – Should I use equipotential bonding in a wooden clubhouse?
Q & A of the Day – Are we now allowed to calculate R1+R2 only?
Q & A of the Day – Why is there a delay in EICR forms from scheme providers?
Q & A of the Day – Is there an individual certificate for disabled toilet alarms?