Question: When installing interconnected smoke alarms with three-core and e cable, using one of the cores as the interconnect, is there an issue with separation of the supply and interconnection circuits within the one cable?

Answer: Reg group 528 of BS7671: 2008, requires every cable or conductor of a Band 1/Band 2 circuit contained within the same wiring system to be insulated for the highest voltage present. Therefore, flat three-core+CPC cable to BS6004 6243Y insulated to 300/500V would achieve this requirement.

To see many more Q & A in Voltimum UK's Experts Area, please click on the link:

www.voltimum.co.uk/consult.php?universe=consult.index.questions

 Back

 Related contacts
NICEIC Group Ltd.,
Warwick House, Houghton Hall Park,
Houghton Regis, Dunstable LU5 5ZX
Tel: +44 (0)1582 531 000
Fax: +44 (0)1582 531 010
Email: enquiries@niceic.com
Web: www.niceic.com
blue arrow pointing right   NICEIC

 For latest electrical industry news, register for Voltimum's free newsletter.
Enter your email address here:
OK

Source: NICEIC & James Hunt

Related information

Related contacts

More News...

Q & A of the Day – Why bond to a plastic gas pipe?
Q & A of the Day – Must I install one double-pole isolator for two consumer units?
Q & A of the Day – What should be the extent of electrical testing in a wooden chalet?
Q & A of the Day – Which code for a batten holder found in a domestic bathroom zone?
Q & A of the Day – Should I use equipotential bonding in a wooden clubhouse?
Q & A of the Day – Are we now allowed to calculate R1+R2 only?
Q & A of the Day – Why is there a delay in EICR forms from scheme providers?
Q & A of the Day – Is there an individual certificate for disabled toilet alarms?
Q & A of the Day – What is the correct method of calculating Zs?